|  | *Mats should be applied with soil fill technique: |  | *Mats should be applied with soil fill technique: | 
|  | **Grade the swale and smooth the top soil, removing any debris and large rocks, |  | **Grade the swale and smooth the top soil, removing any debris and large rocks, | 
| − | **Seed with turf mixture, | + | **Seed with turf grass mixture, | 
|  | **Dig 150 mm anchor trench at the top of the channel,   |  | **Dig 150 mm anchor trench at the top of the channel,   | 
| − | **Secure blanket into the trench with staples every 300 mm. Backfill and compact soil into the trench.  | + | **Secure blanket into the trench with staples every 300 mm. Backfill and compact soil into the trench, | 
| − | **Unroll mat in the direction of flow. Staple as recommended by manufacturer.  | + | **Unroll mat in the direction of flow. Staple as recommended by manufacturer,  | 
| − | **Overlaps should be 150 mm and stapled. Upstream mat should always overlay the downstream mat.  | + | **Overlaps should be 150 mm and stapled. Upstream mat should always overlay the downstream mat,  | 
|  | **Anchor the bottom end of the channel in a similar fashion to the top,   |  | **Anchor the bottom end of the channel in a similar fashion to the top,   | 
| − | **Apply 15-20 mm of topsoil over the TRM, without the use of heavy machinery which can tear the mat and/or compact the soil.  | + | **Apply 15-20 mm of topsoil over the TRM, without the use of heavy machinery which can tear the mat and/or compact the soil,    | 
| − | **An [[Erosion control blankets|ECB]]  may be applied to protect the surface through the first one or two years.  | + | **An [[Erosion control blankets|ECB]]  may be applied to protect the surface through the first one or two years,  | 
|  | **Irrigate until turf grass is established.   |  | **Irrigate until turf grass is established.   | 
|  |  |  |  | 
|  | [[category: materials]] |  | [[category: materials]] |