Difference between revisions of "Bioretention: Construction checklist"
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
| Jenny Hill (talk | contribs) | Jenny Hill (talk | contribs)  | ||
| (12 intermediate revisions by the same user not shown) | |||
| Line 4: | Line 4: | ||
| !colspan =2|Erosion and Sediment Control | !colspan =2|Erosion and Sediment Control | ||
| |- | |- | ||
| − | |style="width: 30px"| | + | |style="width:30px"|  | 
| |Bioretention locations should be blocked from construction traffic and should not be used for erosion and sediment control | |Bioretention locations should be blocked from construction traffic and should not be used for erosion and sediment control | ||
| |- | |- | ||
| || | || | ||
| |Proper erosion and sediment controls should be in place for the drainage area | |Proper erosion and sediment controls should be in place for the drainage area | ||
| + | |- | ||
| + | !colspan =2|Materials | ||
| + | |- | ||
| + | |style="width:30px"|  | ||
| + | |Gravel for the underdrain should be clean and washed; no fines should be present in the material | ||
| + | |- | ||
| + | || | ||
| + | |Underdrain pipe material should be perforated and of the correct size (when specified in design) | ||
| + | |- | ||
| + | || | ||
| + | |A cap should be placed on the upstream (but not the downstream) end of the underdrain (when specified in design) | ||
| + | |- | ||
| + | || | ||
| + | |Biomedia should be tested to confirm that it meets specifications | ||
| + | |- | ||
| + | || | ||
| + | |Mulch composition should be correct | ||
| + | |- | ||
| + | !colspan =2|Elevations | ||
| + | |- | ||
| + | |style="width:30px"|  | ||
| + | |Depth of the gravel and invert of the underdrain | ||
| + | |- | ||
| + | || | ||
| + | |Inverts for inflow and outflow points | ||
| + | |- | ||
| + | || | ||
| + | |Filter media depth | ||
| + | |- | ||
| + | || | ||
| + | |Ponding depth provided between the surface of the filter bed and the overflow structure | ||
| + | |- | ||
| + | || | ||
| + | |Mulch depth  | ||
| + | |- | ||
| + | !colspan =2|Landscaping and Stabilization | ||
| + | |- | ||
| + | |style="width:30px"|  | ||
| + | |Correct vegetation should be planted | ||
| + | |- | ||
| + | || | ||
| + | |Pretreatment area should be stabilized | ||
| + | |- | ||
| + | || | ||
| + | |Drainage area should be stabilized prior to directing water to the bioretention | ||
| + | |- | ||
| + | !colspan =2|The following items should be checked after the first rainfall event, and adjustments should be made as necessary: | ||
| + | |- | ||
| + | |style="width:30px"|  | ||
| + | |Outfall protection/energy dissipation at concentrated inflow should be stable | ||
| + | |- | ||
| + | || | ||
| + | |Flow should not concentrate and should spread evenly over the filter bed | ||
| + | |- | ||
| + | || | ||
| + | |Ponded water at the surface of the bioretenton facility must drain within 24 hours of the end of the storm event. <br> The biomedia should fully drain within a maximum period of 72 hours | ||
| + | |- | ||
| + | || | ||
| + | |Excessive sediment accumulation should not be present | ||
| |} | |} | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| [[category:Checklists]] | [[category:Checklists]] | ||
| [[category:Construction]] | [[category:Construction]] | ||
Latest revision as of 20:08, 4 September 2017
Common construction pitfalls can be avoided with careful construction supervision that focuses on the following aspects:
| Erosion and Sediment Control | |
|---|---|
| Bioretention locations should be blocked from construction traffic and should not be used for erosion and sediment control | |
| Proper erosion and sediment controls should be in place for the drainage area | |
| Materials | |
| Gravel for the underdrain should be clean and washed; no fines should be present in the material | |
| Underdrain pipe material should be perforated and of the correct size (when specified in design) | |
| A cap should be placed on the upstream (but not the downstream) end of the underdrain (when specified in design) | |
| Biomedia should be tested to confirm that it meets specifications | |
| Mulch composition should be correct | |
| Elevations | |
| Depth of the gravel and invert of the underdrain | |
| Inverts for inflow and outflow points | |
| Filter media depth | |
| Ponding depth provided between the surface of the filter bed and the overflow structure | |
| Mulch depth | |
| Landscaping and Stabilization | |
| Correct vegetation should be planted | |
| Pretreatment area should be stabilized | |
| Drainage area should be stabilized prior to directing water to the bioretention | |
| The following items should be checked after the first rainfall event, and adjustments should be made as necessary: | |
| Outfall protection/energy dissipation at concentrated inflow should be stable | |
| Flow should not concentrate and should spread evenly over the filter bed | |
| Ponded water at the surface of the bioretenton facility must drain within 24 hours of the end of the storm event. The biomedia should fully drain within a maximum period of 72 hours | |
| Excessive sediment accumulation should not be present | |