|  | ===Overflow elevation=== |  | ===Overflow elevation=== | 
| − | The invert of the overflow should be placed at the maximum water surface elevation of the practice. i.e. the maximum ponding depth. A good starting point is around 300 mm over the surface of the practice. However, consideration should be given to public safety and time for the ponded water to drain. See [[Bioretention: Sizing#Additional step for system without underdrain|Bioretention]] and [[Stormwater planters]] | + | The invert of the overflow should be placed at the maximum water surface elevation of the practice. i.e. the maximum ponding depth.   | 
|  | + | A good starting point is around 300 mm over the surface of the practice. However, consideration should be given to public safety and drainage time|time for the ponded water to drain.   | 
|  | + | See [[Bioretention: Sizing#Additional step for system without underdrain|Bioretention]] and [[Stormwater planters]] | 
|  | + |   | 
|  | + | Where temporary ponded water is being planned for, include a [[freeboard]] to reduce the chance of localised flooding. | 
|  |  |  |  | 
|  | ===Options=== |  | ===Options=== |